Petrochemical Plant Takes Delivery Of 43 Electric tugs
MasterMover was approached by Fluor, a world-leading engineering and construction company, to design and build a custom solution that could safely move sensitive and awkward loads at Tengiz oilfield in Kazakhstan. Recognizing the need to work with a reputable partner who was experienced in working within the petrochemical industry, Fluor collaborated with MasterMover.
The completely new stainless steel machines needed to be specially treated to comply with the ATEX Zone 1 and EAC directives and as such, had to be suitable for use in areas where there was a risk of potential explosion.
Fluor invited different material handling companies to take part in a tendering process, scrutinizing alternative load moving methods including overhead cranes, winches and motorized skates.
All were rejected on the grounds of safety and efficiency concerns – with a key specification being that the eventual solution needed to be able to move a load of 11,000 lbs. across grating and around tight corners using client-specified carts.
A modified electric tugger was the only answer – albeit one that was cleverly adapted to the stringent demands of a particular and unique working environment. In addition, the client needed to be confident about working with a company that had the design and engineering project management capabilities to deliver a bespoke order of this magnitude.
The overall project deliverables were constrained by a rigorous client documentation pack, the need to adhere to strict international standards and a demanding timeline.
Led by a dedicated Project Manager and Mechanical Design Engineer, an in-depth engineering study was required to collect detailed application data. This had to take into consideration a number of defined turns of various widths and tightness.
The study allowed MasterMover’s Special Projects team to develop a prototype. Working alongside Pyroban, a specialist provider of ATEX conversions, the prototype was based on the most challenging load-moving task faced. It would also ensure the new machines would work in a potentially explosive environment.
ATEX conversion is a complex and time-consuming process, requiring every single electrical component within the body of a machine to be stripped back and re-engineered separately before being brought back together during assembly.
The prototype, which was a modification of an existing MasterMover MasterTow, validated the integration of the electrical enclosure into the machine body through a number of thermal tests in accordance with ATEX Zone 1 restrictions.
After a successful client demonstration at MasterMover around a simulated course on site-specific flooring, production was ready to commence. As the build was towards the end of the project schedule – with potential financial penalties for even a delay of 24 hours – speed and accuracy were of the essence.
To minimize any potential for delay and disruption, a new just-in-time production layout was created at MasterMover’s manufacturing headquarters in Derbyshire. Meanwhile, an already highly skilled MasterMover production team undertook additional ATEX training.
Specialist assembly tools and jigs were designed and manufactured specifically for the build process. These included a support frame to hold the partially wired ATEX enclosure above the main machine carcass during assembly, and a motor loading trolley (which the client would go on to use for the subsequent maintenance of the machines).
Batch production allowed third-party inspectors to visit at regular points to check that the client’s expectations and international standards were being met throughout.
As well as the 39 custom machines, Fluor also ordered 4 stainless steel MasterTugs, spare parts and couplings.
Despite the short lead time for the design and production of a new product, the MasterMover team delivered ahead of schedule – meeting every single requirement along the way.
The completed project is now attracting interest from around the world, as well as other manufacturing sectors.
Thanks to the combination of safety first features and power, it is now possible to keep employees protected from the dangers of flammable vapors and still harness the load-moving capabilities of a MasterMover.
This custom solution is the latest in an innovative range of electric tuggers and tows that are used by many different industries to improve productivity, create smoother workflows and reduce non-value-added activities.
MasterMover designs and manufactures innovative electric tugger solutions to solve complex material handling problems. Alongside our standard product offerings, we're equipped to deliver custom solutions and special projects that meet the unique needs of different applications.